Welcome to your project dashboard!

21 Rylett Crescent

W12 9RP

This week

  • Finalising the Planning Pack - draft to be sent next week.

  • Testing alternative kitchen configuration.

  • Awaiting feedback on bedroom layouts.

(16 Dec 19 - 20 Dec 19) :

Packs

01 Consultation

status: complete

complete: 12 Nov 19

value: £150

01 Survey

status: complete

complete: 20 Nov 19

value: £400

01 Survey

status: in progress

due: 15 Dec 19

value: £1,200

03 Planning

status: not appointed

-

value: £1,200

04 Pricing

status: not appointed

-

value: £1,200

Team

Architect

BetterPAD

projects@betterpad.co.uk

020 3952 7959

Engineer

Simple Works

projects@betterpad.co.uk

020 3952 7959

Party Wall

not yet appointed

-

-

Inspector

not yet appointed

-

-

Statutory Consents

Planning Permission

.

.

requirement:

householder planning permission required

action:

submitted : 10 Jan '20

decision : 10 Mar '20

Party Wall

.

.

requirement:

notice to be served on no.172 and no. 176

action:

party wall surveyor to be appointed

Building Regulations

.

.

requirement:

Full Plans Approval Required

action:

Inspector to be appointed

fire report to be commissioned

Payments

No. 205, £1,200

sent: 06 Dec 19

due: 20 Dec 19

not yet paid

No. 201, £1,200

sent: 06 Dec 19

due: 20 Dec 19

overdue

No. 197, £600

sent: 06 Dec 19

due: 20 Dec 19

paid